Proper installation is essential to get the best performance, appearance, and service life from an FRP wall covering.
Glasliner is a fiberglass-reinforced plastic (FRP) panel manufactured with polyester resin and fiberglass. It is designed for wall applications where durability, hygiene, moisture resistance, and ease of cleaning are important.
This step-by-step guide explains the basic installation process for Glasliner wall panels, from surface preparation and cutting to adhesive application, molding installation, and final cleaning.
Before you begin: Preparing the area and materials
A successful Glasliner installation starts with careful planning and surface preparation.
Before installing the panels, define the total area that will be covered and determine the most efficient panel layout based on the dimensions of the sheets.
Planning the installation before cutting helps reduce unnecessary material waste and makes it easier to align joints, corners, electrical outlets, switches, and other wall elements.
Preparation of the wall or base surface
The wall or base surface should also be inspected. It needs to be clean, free of debris, and without significant irregularities. When installing over concrete block, a leveling coat of plaster or a similar material is commonly used to create an even surface.
Before proceeding, inspect every panel. If one has a visible imperfection, it is best to set it aside and address the issue with the supplier before installation rather than after it has been installed.
1. Seal the Installation Surface
Seal the surface where Glasliner will be installed using a neutral or antibacterial sealer.
Apply the sealer with a roller or brush and allow it to dry completely before continuing.
2. Plan the Installation Area
Define the area where Glasliner will be installed and determine the best way to cover it according to the dimensions of the panels.
3. Cut the Glasliner Panels
Cut the panels to the required dimensions.
The installation guide recommends using:
- Sheet metal shears
- Electric saw
- Manual saw
4. Measure Outlets, Switches, and Cables
Measure the location of outlets, switches, cables, and any other elements that need to be considered once Glasliner is installed.
5. Mark the Panel
Transfer the measurements of outlets, switches, cables, and other required openings onto the Glasliner surface.
6. Make the Required Openings
Perforate the panel using a hole punch or jigsaw.
7. Prepare the Moldings
Cut and prepare the moldings required for each joint and finishing point of the installation.
Use sheet metal shears to cut the moldings.
The guide identifies the following molding options:
- Outside angle
- Inside angle
- Outside corner
- Inside corner
- Top cap
- Division bar
Glasliner Wall Installation
Once all pre-installation steps have been completed, continue with the wall installation.
Step 1: Apply the Adhesive
Apply the appropriate adhesive to the back surface of the Glasliner panel, on the opaque side.
Follow the adhesive manufacturer’s recommendations and use a notched trowel.
Before applying the adhesive, make sure the back surface of the panel is dry and clean, free of:
- Dust
- Moisture
- Dirt
- Grease
Step 2: Place the Panel on the Wall
Position the Glasliner panel on the wall.
Before placing it, make sure the wall is clean and dry.
Step 3: Install the Moldings
Install the corresponding moldings between one panel and the next.
Leave approximately ½ cm of space between the panel and the molding stop to allow the panel to adjust to temperature changes.
Step 4: Press the Panel Against the Wall
Using a roller or rubber mallet, press the Glasliner panel against the wall.
Remove any air that may have become trapped between the panel, adhesive, and wall.
The entire surface of the panel should remain in direct contact with the adhesive.
Step 5: Remove Excess Adhesive
Clean any adhesive that extends beyond the panel after installation.
Use:
- A cloth
- A plastic spatula
to remove excess adhesive.
Step 6: Repeat the Process
Repeat the previous steps until all Glasliner panels have been installed.
Step 7: Allow the Installation to Dry
Allow the installation to dry for 24 hours.
Afterward, clean the entire installed surface using a damp cloth.

Glasliner Wall Installation Checklist
Before finishing the installation, confirm that:
- The installation surface was sealed and completely dry.
- Panel dimensions and wall openings were measured before installation.
- The back of each panel was clean and dry before applying adhesive.
- Adhesive was applied to the opaque side using a notched trowel.
- The wall was clean and dry before panel placement.
- Approximately ½ cm of space was left at the molding stop.
- Trapped air was removed using a roller or rubber mallet.
- Excess adhesive was removed.
- The completed installation was allowed to dry for 24 hours.
Following this sequence helps ensure the Glasliner wall installation is completed according to the recommended process.
Frequently Asked Questions
Can polyester panels be installed over existing walls?
Yes. This is common as long as the existing surface is level, clean, and in suitable condition to receive the panel.
Where are Glasliner panels commonly used?
They are commonly used in spaces where hygiene, frequent cleaning is important, including industrial kitchens, food processing areas, commercial bathrooms, and high-traffic spaces.